Lifting of Naphtha Splitter
The project involved coordinating a complex multi-crane operation to lift a 152-ton Naphtha Splitter onto a foundation, overcoming the challenges of precise load distribution and crane positioning.
Employees: 45
Progress: 85%
PROJECT SCOPE
To find a solution to top and tail the Naphtha Splitter and erect it on the foundation (Ht:9m)
CHALLENGES FACED
SOLUTION PROVIDED
After examining the site condition, a selection of 2 cranes were made. Liebherr LR 1600/2 (600T crawler crane CR-14) with SDBW 72m main boom configuration was used as the main crane and Liebherr LTM 1400-7.1 (400T mobile crane) was used as a tailing crane to successfully top and tail the naphatha splitter and carefully erect it on the foundation.