Top and Tailing of Offshore Jacket
The project was completed successfully through the coordination of various cranes, using the appropriate equipment to ensure the structure was positioned accurately on the base in the shortest time possible.
Employees: 18
Progress: 100%
PROJECT SCOPE
To find a custom solution to top and tail the complete fabricated structure and align it with the base jacket structure.
CHALLENGES FACED
• Handling a large and sensitive offshore structure during the top and tail process. • Coordination between cranes to ensure precise alignment with the base structure.
SOLUTION PROVIDED
A selection of 3 cranes were used. Our Liebherr 600T crawler crane with 84.0M boom SDBW was used as the main crane, a 400T crawler crane with 64.0M boom, and our Liebherr 1200T mobile crane were used as tailing cranes to successfully top and tail the entire structure and then carefully position it over the base structure for welding.